The modalities for operational and maintenance arrangements of 450-MW Baglihar Hydro Electric Project, all set to be commissioned during next month, were discussed here today at a high level meeting of officers of Power Development Corporation chaired by Advisor to Governor Mr. C. Phunsog.
Commissioner/Secretary PDD Mr. Sandeep Naik, Managing Director JKPDC Mr. Shantmanu, Executive Director PDC Mr. A.R. Kak, Chief Engineer Generation Jammu, Director Finance were among other officers who attended the meeting.
The meeting decided that senior and junior engineers besides technicians of the department would be imparted necessary operational trainings of various machines of the project by the experts.
The meeting was informed that the spinning and rolling of the machines was currently going on and first unit of 150 MW capacity would start generating electricity from next month.
The Advisor also discussed modalities for laying 400 KV transmission line from Baglihar to Kishnapur with the engineers and asked them to expedite the pace of work for starting the first unit of this prestigious project.