X

Pipes stores and Construction company of Peshawar pipes

 If there are images in this attachment, they will not be displayed.  Download the original attachment

Completed Projects of M/S Peshawar Pipes & Construction Company

 

S.N

Name of the Project

Department

Amount

 

Remarks

1

WSS Dagai Khass Korona Hoti  Mardan.

PHE Mardan.

14,56,53,193.

Completed

2

WSS Lachi District Kohat (Lachi Bala)

PHE Kohat

           5,84,67,645.

Completed

3

WSS Lachi District Kohat (Lachi Payan)

PHE Kohat

4,36,41,783.

Completed

4

WSS Kohat City, Kohat

D.D.O-WS & S Kohat.

4,35,92,578.

Completed

5

WSS Peshawar

NUDP Peshawar

4,06,26,144.

Completed

6

WSS Charsadda

NUDP Peshawar

3,70,15,866.

Completed

7

WSS Chitral

NUDP Temargara

3,61,31,753.

Completed

8

WSS Dir Upper

NUDP Temargara

3,46,08,634.

Completed

9

Different Water Supply Schemes in Peshawar. (2008-9)

D.D.O-WS & S Peshawar

3,71,04,600.

Completed

10

Different Water Supply Schemes in Peshawar. (2009)

D.D.O-WS & S Peshawar

3,26,68,540.

Completed

11

WSS Ayun

D.D.O-WS & S Chitral

2,41,06,000.

Completed

12

WSS Khoth Phase I

D.D.O-WS & S Chitral

2,13,42,539.

Completed

13

W.S.S Nirgah to Dir Town Dir. (KPP)

D.D.O-WS & S Dir

1,66,00,000.

Completed

14

Replacement of Pipe line at Mardan

D.D.O-WS & S Mardan

1,56,83,910.

Completed

15

Widening and Carpeting of Boni Buzund Torkhow Road.

C & W Division Chitral.

1,08,67,000.

Completed

16

Rehabilitation of Roads at Darosh.

Public Works DepartmentChitral.

 

Completed

17

Construction of Road at Singoor

Public Works DepartmentChitral.

 

Completed

18

WSS Pawaka Peshawar.

PHE Peshawar.

65,25,000.

Completed

19

WSS Sheikh Muhammadi Peshawar.

PHE Peshawar

68,78,000.

Completed

20

WSS Kambar & Badin Kilay (Badin Kilay portion)

D.D.O-WS & S Peshawar

66,49,000.

Completed

21

Supply of Pipes

A.K.R.P Chitral

60,00,000.

Completed

22

W.S.S Dir Town under(Dera)

D.D.O-WS & S Dir

66,00,000.

Completed

23

WSS Kambar & Badin Kilay (Badin Kilay – R/Main)

D.D.O-WS & S Peshawar

56,31,812.

Completed

24

WSS Batangi

TMA Balakot

51,17,700.

Completed

25

WSS Diyaroon Kilay

D.D.O-WS & S Peshawar

49,53,000.

Completed

26

Supply of G.I pipes (Gorro Bandagai)

D.D.O-WS & S Temergara

45,17,800.

Completed

27

Drain & Street Pavement

D.D.O-WS & S Peshawar

44,05,055.

Completed

28

       

29

WSS Badhaber Hurzai

D.D.O-WS & S Peshawar

41,10,497.

Completed

30

WSS Badabher Police Station Peshawar.

PHE Peshawar.

38,11,000.

Completed

31

WSS Shahab Khel

D.D.O-WS & S Peshawar

37,10,000.

Completed

32

WSS Kambat & Badin Kilay

D.D.O-WS & S Peshawar

34,11,200.

Completed

33

WSS Darmangi Peshawar.

PHE Peshawar.

32,92,908.

Completed

34

Siphon Irrigation channel Orgoch Chitral

Distt. Council Chitral

28,00,000.

Completed

35

WSS Sheikhan

D.D.O-WS & S Peshawar

27,71,000.

Completed

36

WSS Shahdam Khander Buner

Distt. Council Buner

27,51,000.

Completed

37

Water Supply delivery line of 6’’ Ñ„ at R.B.CTarbela

WAPDA Tarbela Dam Project Tarbela

17,23,191.

Completed

38

WSS  Rehan Abad

D.D.O-WS & S Peshawar

27,18,000.

Completed

39

Provision of T/W at PAF Camp Badhaber

MES,(PAF) Peshawar

26,47,885.

Completed

40

WSS  Gulozai Muhammad Zai

D.D.O-WS & S Peshawar

26,17,000.

Completed

41

W.S.S Dak Ismail Khel

D.D.O-WS & S Nowshera

26,00,000.

Completed

42

WSS Garhi Shah Mohammad

D.D.O-WS & S Peshawar

25,96,425.

Completed

43

WSS Kawai

TMA Balakot

24,84,000.

Completed

44

Provision of tube well in replacement of tube well No. 1, at PAF Base Kohat

MES, AGE(Air) Kohat

24,46,991.

Completed

45

WSS Mushtaq Abad

D.D.O-WS & S Peshawar

24,00,000.

Completed

46

Replacement of Water Supply Pipeline at Khushal Camp at PAF Base Kohat

MES,AGE(Air) Kohat

23,60,000.

Completed

47

Water supply Scheme Gul Abad

C.I.P Town – I

21,00,000.

Completed

48

Supply of G.I.Pipes of different sizes with

accessories

Municipal Corporation Peshawar

20,00,000.

Completed

49

Providing and fixing of G.I pipeline Canal Town

Municipal Corporation Peshawar

20,00,000.

Completed

50

Provision of T/W at Canal Town

Municipal Corporation Peshawar

20,00,000.

Completed

51

Supply of Pipes

Town-II

20,00,000.

Completed

52

WSS Kaniza

D.D.O-WS & S Peshawar

20,00,000.

Completed

53

WSS Gul Abad

D.D.O-WS & S Peshawar

20,00,000.

Completed

54

DWSS Pawaka

D.D.O-WS & S Peshawar

19,97,233.

Completed

55

WSS Achini Payan

D.D.O-WS & S Peshawar

19,77,000.

Completed

56

WSS Budhai

D.D.O-WS & S Peshawar

19,18,362.

Completed

57

WSS Shaheed Abad No.3 Dist pesh

PHE Peshawar

19,13,220.

Completed

58

W.S.S Canal Town

Town-III

19,00,000.

Completed

59

W.S.S Nodhia Peshaear.

D.D.O-WS & S Peshawar

18,94,765.

Completed

60

DWSS Yakatoot III

D.D.O-WS & S Peshawar

18,86,000.

Completed

61

WSS Tablieghi Markaz Hangoo.

District Council Hangoo

18,68,000.

Completed

62

WSS P/H Lakhty Gara (Khan Mast Colony)

D.D.O-WS & S Peshawar

18,38,916.

Completed

63

WSS Pump/ House Sirki Gate (inside)

D.D.O-WS & S Peshawar

18,30,736.

Completed

64

WSS Swati Phattak

D.D.O-WS & S Peshawar

17,92,193.

Completed

65

Replacement of 8’’ Ñ„ pipeline sobra city Tarbela

XEN Civil Division – II Tarbela Dam project.

17,43,797.

Completed

66

WSS Shaheed Abad No. III

PHE Peshawar

17,41,000.

Completed

67

W.S.S Sikandar Town

D.D.O-WS & S Peshawar

17,14,680.

Completed

68

Supply of G.I Pipes (Kumber)

D.D.O-WS & S Temergarah

17,14,100.

Completed

69

WSS Malakandher

D.D.O-WS & S Peshawar

17,00,000.

Completed

70

WSS Madina Colony

D.D.O-WS & S Peshawar

16,98,400.

Completed

71

WSS Gul Bela

PHE Peshawar

16,85,320.

Completed

72

WSS At Village Gul Bela

PHE Peshawar

16,85,320.

Completed

73

W.S.S Masho Pake

D.D.O-WS & S Peshawar

16,71,877.

Completed

74

WSS Muryamzai

D.D.O-WS & S Peshawar

16,64,629.

Completed

75

WSS Chota Garhi

D.D.O-WS & S Peshawar

16,57,000.

Completed

76

WSS Mohallah Ajab Khan

D.D.O-WS & S Peshawar

16,50,000.

Completed

77

WSS Asad Anwar Colony

D.D.O-WS & S Peshawar

16,42,500.

Completed

78

WSS Chamkani – II

D.D.O-WS & S Peshawar

16,35,000.

Completed

79

WSS Tehkal Payan – I

D.D.O-WS & S Peshawar

16,22,400.

Completed

80

WSS Achini Bala

D.D.O-WS & S Peshawar

16,22,400.

Completed

81

WSS Achini Bala Landi

D.D.O-WS & S Peshawar

16,22,400.

Completed

82

WSS Sufaid Dheri

D.D.O-WS & S Peshawar

16,22,400.

Completed

G. H. Farooqui: Free Lance Journalist from Chitral Pakistan and Human Rights Activist as well as Social Worker and Registered Volunteer
Related Post